Downderry School, London
- 6 week project, 7 days a week
- No margin for error or deadline extension
- 1 site manager, 4 supervisors and 35 operatives on site
- Removal of lathe and plaster ceilings throughout the school to access voids above for removal of residue asbestos
- Value: £270,000
- Challenges
- Strict deadline – school was shut down because of asbestos and the opening date was 15th December, after refurbishment
- Planning, project management
- EAS had to meet six week deadline to enable refurbishment contractor to complete their work
- Deadline was met – and finished three days early